29
/
en
AIzaSyAYiBZKx7MnpbEhh9jyipgxe19OcubqV5w
June 15, 2023
Create
Public Timelines
Library
FAQ
For education
Cabinet
For educational institutions
For teachers
For students/pupils
Download
Export
Duplicate
Embed
385 views
0
0
SL-1 Reactor Accident Timeline
Created by
Darran Jones
⟶ Updated 30 Nov 2018 ⟶
List of edits
Comments
Events
SL-1 Shut Down for Planned Maintenance
Work on the Reactor Core is Completed, and the Accident Occurs
Request for the Plant to be Built made by the AEC
Construction was Started by the Fegles Construction Company
Design and Proposed Operation of the Reactor were Reviewed
Initial Critical Operation Takes Place
Test Operations Terminate After 500 Hour run
CEI "Part-Time Project Manager" Writes letter to the AEC Contracting Officer's Representative Requesting that Shift Supervisors not be Required for Routine Supervision of Plant Operation During Night Shifts
Complete technical review of the reactor and its proposed operation was made
SL-1 Achieved its full power rating of electricity and space heat
40-Hour Xenon run was Made
Strips of Cadmium were Inserted in two of the T-rod Control Shrouds due to Reduced shut-down margin resulting from the boron loss
Army Reactors Branch Stated that the Procedures and Manuals Turned over to CEI by ANL were not Satisfactory for use by CEI
Test Operation by CEI for the Windsor Nuclear Safety Committee takes place
Cold Critical Experiments begin
SL-1 turned over to CEI for Operation
1000 Hour Sustained Power Run was concluded
Fuel Elements first Removed from the Core and Inspected by CEI and ANL Personnel
Initial Discovery of Bowing of Boron Strips
Large amounts of the boron strips were missing from some fuel elements and the fuel elements in the center of the core were extremely difficult to remove by hand. (Large loss of Boron attributed to larger rate of gain of reactivity)
It was Noted During the Second Periodic Inspection, that Central Fuel Elements were Difficult to Remove
It Appeared that the Core was Gaining Reactivity Faster that Predicted
Plant Superintendent orders shifts to perform complete rod travel exercise 4 hours into the start of their shift.
Operation Supervisor orders complete rod travel exercise on the graveyard and subsequent shifts
Plant Superintendent Orders not to perform control rod exercises during 2.56 MW power run
Periods
Two Remaining Bodies and Equipment and Records Recovered
Argonne National Laboratory Works on Designing, Testing, and Initial Operation of the Reactor Plant
Combustion Engineering, Inc. gets a Contract to run the Facility
The Reactor is Operated at a Power level of 3MW
Plant Shut Down for Maintenance, Modification, and Inspection