Device v2 Last Call 4/6/20-4/10/20 (apr 6, 2020 – apr 10, 2020)

Description:

Sr Project team will have final product completed by the end of this work phase. This work phase will include finalization of assembly (glue/screw/solder everything in place). April 10th is the drop-dead date for having the product finalized.

Consider this to be the week where the "finishing touches" are done.

Any eChemion 'wishlist' items or minor requests may be accepted at this time but no major changes can be made at this point.

Added to timeline:

29 May 2020
0
0
250
Project Timeline
EECS Sr Project timeline

Date:

apr 6, 2020
apr 10, 2020
~ 4 days