ISEC signs Subcontract with Austin Commercial
Baseline Schedule ISEC Install Start Date
Baseline Schedule ISEC Install Finish Date
04/04/2018 Schedule Substantial Completion
04/04/2018 Schedule ISEC Finish Date
01/20/2017 Recovery Schedule ISEC Start Date - Capri Ballroom
01/20/2017 Recovery Schedule ISEC Start Date - Grand Ballroom
01/20/2017 Recovery Schedule ISEC Finish Date - Grand Ballroom
01/20/2017 Recovery Schedule ISEC Finish Date - Capri Ballroom
ISEC Issues COP 46-R1 for Schedule Compression
Per 7/17/18 Email 2nd impact – Builder’s Risk Claim 015.016096.MI
Per 7/17/18 Email 1st impact – Builder’s Risk Claim 015.016036.MI
Per 7/17/18 3rd impact – Builder’s Risk Claim 015.016531.M Email Hurricane Irma