FP0001 Timeline
Created by
Charlie D
⟶ Updated 7 Oct 2018 ⟶
List of edits
Timelines by
Charlie D
:
10 months ago
0
0
400
Killing Time
Comments
Events
Project Start
Submitted alternative design, C02 V01 Turn valve
Completed C01 V03
Completed C02 V02 Production
Completed C02 V02 Concept Models.
Received Concept 02 V03 Valve Prototypes
Short Version: Created and submitted for review.
Annular Seal Change
Pre-Project Overview Meeting
Invoice 001
Invoice 002
Submitted Overview of Concept 01
C01 V01 was chosen by Ferring
Invoice 003
Invoice 004
Invoice 005
Invoice 006
Invoice 007
Decision made to change to round spout
Project critical path revised. Standard bottle, no DC
Periods
B&M MFG Of Concept 02 V01
Material research. Start conceptual designs for possible packages.
Started C01 V01 V02 V 03
Continued Worked on C01
Design and Prototyping Of C02 V03
Single Point MFG Material Specimin Container
Vendor Search
Continued Worked on C01 Changing spout to round shape with new burst pouch
Refined turn valve concept
Refined turn valve concept (copy)
Altered C02 V02 to be machined version for B&M
Managed Vendors, and refined productin version