Unit Tx 3
Created by
Dhiafullah Ezani
⟶ Updated 30 Sep 2018 ⟶
List of edits
Timelines by
Dhiafullah Ezani
:
30 Sep 2018
0
0
376
U1 MI (21-28 Sept 2018)
30 Sep 2018
0
0
341
Station Transformer
30 Sep 2018
0
0
325
Station Transformer 2
Comments
Events
PGAU 3 Unit Tx Failed (01 Sept 2017)
RCA with SGPK RE (19 Sept 2017)
REMACO 1st site visit (04 Sept 2017)
Request quotation with GE (19 Oct 2017)
HQ Way Foward Meeting (06 Dec 2017)
TRC Presentation (16 Jan 2018)
Tender Submitted (08 Mac 2018)
Design Review (24 Aug 2018)
API & FAT (03-05 Sept 2018)
Installation & Commissioning (05-26 Oct 2018)
ABB site visit (27 Dec 2017)
LOA (07 Jun 2018)
PO (10 July 2018)
OA (05 July 2018)
Site Visit (19 April 2018)
Closed tender (10 May 2018)
Evaluation tender spec (16 May 2018)
Spec Preparation (Open Tender) (04 Feb 2018)
Meeting to engage REMACO (15 Sept 2017)
Disscussion to open tender (ELCM) (25 Oct 2017)
Request quotation with REMACO & Schneider (08 Sept 2017)