Timeline - Wave 1
Creado
Cullen Caballero
⟶ Actualizado 14 feb 2018 ⟶
List of edits
Comentarios
Eventos
KPI Project Start 1/16
Vertiv projected Final CoA Delivered 2/5
New projected Final CoA Delivery 2/16
Build Complete 3/6
Go-Live Wave 1 8/1 (July Close)
Go-Live Wave 2 10/1 (September Close)
Wave 2 Build Start 3/24
Períodos
System Integration Testing (SIT) 3/26 - 4/13
Unit Testing 3/7 - 3/23
Next Sprint of Wave 1 4/14 - 6/4
Next Sprint of Wave 1 6/25 - 7/9