Kick-off Meeting (2 Feb 2018)
Requirement Specification Document (12 Feb - 14 Feb)
Design (12 Feb - 2 Mac)
Development (19 Feb - 11 May)
Testing & Deployment (5 Mac - 11 May)
Integration Testing (30 Apr - 4 May)
Installation & Configure System (7 May - 11 May)
Test System (14 May - 25 May)
UAT & FAT (28 May - 1 Jun)
Sign-Off (4 June 2018)
Maintenance (1 June - 1 Dec)