33
/
AIzaSyB4mHJ5NPEv-XzF7P6NDYXjlkCWaeKw5bc
November 1, 2025
1930754
519920
2
Public Timelines
FAQ Get premium

Work begins on addittional Preperation for Spray Seal works (aug 24, 2020 – sep 22, 2020)

Description:

FH picks up additional day shifts to prepare areas for spray seal accelerated due to Covid restrictions.
1,030t of Regulation & 1,054t of 20SI across 12 sites

Added to timeline:

24 Jun 2021
0
0
209

Date:

aug 24, 2020
sep 22, 2020
~ 29 days