Work begins on addittional Preperation for Spray Seal works (aug 24, 2020 – sep 22, 2020)
Description:
FH picks up additional day shifts to prepare areas for spray seal accelerated due to Covid restrictions.
1,030t of Regulation & 1,054t of 20SI across 12 sites
Added to timeline: