33
/
AIzaSyAYiBZKx7MnpbEhh9jyipgxe19OcubqV5w
August 1, 2025
Public Timelines
Menu
Public Timelines
FAQ
Public Timelines
FAQ
For education
For educational institutions
For teachers
For students
Cabinet
For educational institutions
For teachers
For students
Open cabinet
Create
Close
Create a timeline
Public timelines
Library
FAQ
Edit
Download
Export
Duplicate
Premium
Embed
Share
Detailed Saeed
Category:
History
Updated:
6 months ago
0
0
94
Contributors
Created by
Saeed Youssef
Attachments
Comments
New timeline
By
Saeed Youssef
2 Aug 2023
0
0
172
New timeline
By
Saeed Youssef
2 Aug 2023
0
0
160
saeed
By
Saeed Youssef
7 months ago
0
0
100
Saeed Phases
By
Saeed Youssef
6 months ago
0
0
79
Ehouse
By
Saeed Youssef
1 months ago
0
0
71
time line1
By
Saeed Youssef
8 months ago
0
0
57
Time line
By
Saeed Youssef
7 months ago
0
0
53
saeed 2
By
Saeed Youssef
7 months ago
0
0
52
Time Line
By
Saeed Youssef
1 months ago
0
0
39
Events
Employer’s Taking Over Date 14 May 2026
Grouping
Group of events
Events
Power Transformers LOA signature date 11 Nov 2024
Powe Transformer Phase 2 Delivery 13 March 2026
Periods
Power transformer Phase 2 Delivery
Phase 2 Milestones
Events
Power Transformer delivery for Phase 2 15 March 2026
HV Substation Mechanical Completion (MC) [Power transformers and associated equipment ] - Phase 2 25 April 2026
Remote End SS Works Completed 10 May 2026
Substation Hot commissioning 10 May 2026
Periods
Phase 2 Execution Duration from :13 January 2025 till :18 May 2026
Erection Works
Grouping
Erection Works - Phase 1
Events
Erection activities commencement 20 aug 2025
Erection activities Completed Phase 1 16 oct 2025
Periods
Erection Activities
Project execution
Events
LOA for HV EPC Contract 13 January 204
Site Handover to Siemens 20 January 2025
HV EPC Contract Signature 31 January 2025
Outdoor Mechanical & Electrical installation Completed 30 October 2025
All Equipment Received at site Phase 1. 15 October 2025
HV Substation Mechanical Completion (MC) - Phase 1 7 November 2025
Remote End SS Works Completed 11 November 2025
Ready for Energization 18 November 2025
Periods
Phase1 Execution Duration from :13 January 2025 till :18 November 2025
Civil Works Phase 1
Events
Outdoor/Switchyard foundation, Civil Work Completed 28 August 2025
Control Building Completed (Ready to receive equipment inside) 27 September 2025
Civil Works Commencement 27 March 2025
Civil Works complection 28 spetember 2025
Periods
Civil Works on Progress
Engineering
Events
Enginering Commencement 16 February 2025
All Documentation Issue For Construction (IFC) 28 April 2025
Periods
HV EPC Engineering Works
Power transformer
Events
Phase 1 Power Transformers Site delivery 25 September 2025
Power Transformers LOA signature date 11 Nov 2024
Periods
Power transformer Phase 1 Delivery
About & Feedback
Terms
Privacy
Library
FAQ
Support 24/7
Cabinet
Get premium
Donate
The service accepts bank transfer (ACH, Wire) or cards (Visa, MasterCard, etc). Processed by Stripe.
Secured with SSL
Comments