Linea de Tiempo San Bartolo
Category:
Other
Updated:
10 Aug 2021
0
0
155
Contributors
Created by
LUIS
Attachments
Comments
Events
INICIO CONTRACTUAL 03.12.2015
CULM. DE PLAZO CONT. 27.09.2016
CUL. AMP. DE PLAZO 13.02.2017
REINICIO DE OBRA UT-04 US-01 19-06-2019
CULM. CONTRACTUAL 14.12.2019
PARALIZ. DE OBRA POR ESTADO DE EMERGENCIA 15.03.2020
REINICIO DE OBRA 11.08.2020
FECHA PROBABLE DE CULM. 30.11.2021
Periods
PLAZO CONTRACTUAL 300 DC
PERIODO DE ARBITRAJE POR UT-04 US-O1 519 DC
IMPLEMENT. LAUDO ARBITRAL 336 DC.
EJEC. ADICONAL UT-04, US-01 180 DC
RETRAZO DE OBRA 92 DC
PLAZO DE EJECUCION ESTIMADO DE MEDIA TENSIÓN 60 DC.
OBRA RETRAZADA 385 DC. HASTA EL 10.08.2021
AMPLIACIONES DE PLAZO (03-10) 139 DC
PARALIZACION DE OBRA POR ESTADO DE EMERGENCIA (147 D.C)
TRAMITES A LUZ DEL SUR POR SISTEMA DE MEDIA TENSION
RECEPCION DE OBRA DEL 01.12.2021 AL 31.01.2022
TRANSFERENCIA DE OBRA DEL 01.02.2022 AL 28.02.2022
About & Feedback
Terms
Privacy
Library
FAQ
Support 24/7
Cabinet
Get premium
Donate
The service accepts bank transfer (ACH, Wire) or cards (Visa, MasterCard, etc). Processed by Stripe.
Secured with SSL
Comments