33
/
AIzaSyAYiBZKx7MnpbEhh9jyipgxe19OcubqV5w
August 1, 2025
Public Timelines
Menu
Public Timelines
FAQ
Public Timelines
FAQ
For education
For educational institutions
For teachers
For students
Cabinet
For educational institutions
For teachers
For students
Open cabinet
Create
Close
Create a timeline
Public timelines
Library
FAQ
Edit
Download
Export
Duplicate
Premium
Embed
Share
XTRB
Category:
Other
Updated:
30 Jun 2020
2
0
290
Contributors
Created by
tashdelen
Attachments
Comments
XTRA migration cut-over time line
By
tashdelen
28 Mar 2022
0
0
190
Events
Inbound Go-Live 14 Sep
Outbound Go-Live 28 Sep
System Go-Live & Golden Tests 1 Sep
Periods
Plan 25 June - 6 July
Prepare 6 July - 3 Aug
Practice 3 Aug - 24 Aug
Provide 24 Aug - 9 Oct
Pack-Up 9 Oct - 16 Oct
Project Intitation 25 June - 6 July
Gap Analysis 1 July - 6 July
Tibco - WMS - Packing App. Development 6 July - 3 Aug
IT Testing (SIT) 3 Aug - 13 Aug
End User Testing 13 Aug - 24 Aug
Deployment 24 Aug - 1 Sep
Operational Dry Run 1 Sep - 14 Sep
HyperCare 14 Sep - 9 Oct
User training 13 Aug - 24 Aug
About & Feedback
Terms
Privacy
Library
FAQ
Support 24/7
Cabinet
Get premium
Donate
The service accepts bank transfer (ACH, Wire) or cards (Visa, MasterCard, etc). Processed by Stripe.
Secured with SSL
Comments