Ipoh Project Timeline
83 Solar PV Rooftop Sites
Created by
Faiz Firman
⟶ Updated 12 Dec 2017 ⟶
List of edits
Timelines by
Faiz Firman
:
26 Feb 2020
0
0
306
Chilli Timeline
1 Aug 2019
0
0
178
CSR Project
Comments
Events
Agreed Decision on structure of the deal
Finalization on tripartite agreement - MAIPk, RNE, Kinetix
Submission of documents to financiers - Simulation - Projections - Technical Specifications - SLD
Expected Approval of Financing
Event progress
Site Visit, SLD Design
Project completed - Installation Done at all 83 Sites - Average of 16 sites per month
TNB Testing & Comissioning