Ece Senior Project Timeline
Full Semester
Created by
Alfredo
⟶ Updated 8 Dec 2017 ⟶
List of edits
Comments
Events
Partner Selection Sep 8
Team Chosen Sep 10
First Project Selected Sep 20
Roles Decided Sep 21
Potential Flaw Encountered Sep 29
Second Project Selected Sep 30
Established Goals Oct 3
Project Constraints Oct 11
Project Constraints (cont.) Oct 18
Third and Current Project Chosen Oct 27
Goals Established Oct 31
Project Constraints Nov 1
Flowchart Nov 8
Flowchart (cont.) Nov 14
Flowchart (cont.) Nov 15
Article Research Nov 18
Patent Research Nov 22
Selection Finalized Nov 28
Professor Discussion Patents Nov 29
Started Powerpoint Dec 1
Powerpoint (cont.) Dec 2
Powerpoint Completed Dec 3
PowerPoint Presentation Dec 6
Handed In Report Dec 8
Order Components Dec 28th
Discuss Final Design Jan 8th
Test/Establish Desired Humidity Levels Jan 12
Start Assembly Jan 28th
Assemble Code For Humidity Detection System Feb 4
Continue Code Feb 16
Test Code With Hardware Feb 22
Resolve Any Potential Code Issues Mar 5
Discuss Project Progress With Professor Mar 16
Fix Issues Noted By Professor Mar 25
Finish Project for Testing Mar 28
Continue Testing Apr 4
Implemented Changes Noted During Testing Apr 10
FInish Project, Established Ready Product Apr 16