41
/
AIzaSyB4mHJ5NPEv-XzF7P6NDYXjlkCWaeKw5bc
May 31, 2026
Create a timeline
Public Timelines
For organizations
For companies
For educational institutions
For teachers
For students
Dashboard
For educational institutions
For teachers
For students
Dashboard
FAQ
Close
Create a timeline
Public timelines
FAQ
About & Feedback
Terms
Privacy
FAQ
Support 24/7
Dashboard
Get premium
Donate
Edit
Download
Export
Duplicate
Premium
Embed
Share
SE FTZ - Timeline
Category:
Other
Updated:
9 Dec 2019
0
0
297
Contributors
Created by
Fernanda G.
Attachments
Comments
SE Recife II - Timeline
By
Fernanda G.
22 Mar 2022
0
0
218
Events
11.05.17 Assinatura do Contrato
30.03.18 Estruturas Existentes Término das discussões
11.08.18 Data de Energização BaseLine
30.03.19 (penalty date) Data de Energização Termo Aditivo n° 4
Pedido de EoT até 14.10.19 Pelo atraso no TA n° 4
Dez./18: Início dos Trabalhos da Energy Como Subcontratada
27.02.19: Recebimento do Termo Aditivo n° 04
12.04.19: Entrega das Estruturas Adicionais em campo
Novo Pedido de EoT até Jan./20 --> Suspensão das Obras por Atraso de Pagamentos da Chesf (to be send)
Mar/20: Data Prevista de Conclusão
Periods
Paralisação da Obra pela Energy Atraso de Pagamentos Chesf
About & Feedback
Terms
Privacy
FAQ
Support 24/7
Dashboard
Get premium
Donate
The service accepts bank transfer (ACH, Wire) or cards (Visa, MasterCard, etc). Processed by Stripe.
Secured with SSL
Comments