IROPS R2 - Timeline
Created by
Ricardo Sanchez Delgado
⟶ Updated 9 Nov 2018 ⟶
List of edits
Comments
Events
Project Started
Project R2- NO GO
July Release
May Release
February Release
Inception
3 Approaches
Repositories
Change of Approach
No Database in Memory
Gemfire as Database in Memory
Delivery Versions for QMO
No QMO Resources to Test
SWA TL Changed
Switch PDC/SDC
Kafka SASL Required
Kafka CyberArk Required
FES Performance Issues
Gemfire Partially Removed
FES NFR Issues
R3 - Inception
R3 - Microservices Approach
R3 - Re-Inception Using AWS and Lambda Functions
R3 - Started
No PERF Environment
No PERF Environment
QMO Perf Started
QMO Certification Stopped
QMO Certification Stopped
Kafka SASL Implementation Done
Kafka Cyberark Implementation Done
Kafka Instability
No PERF Environment
Release Moved to Aug / Sept
QMO NFR Testing
FES Manual / Automatic Switch Failing
Manual/Automatic Switch Fixed
FES NFR Kafka Switch Instability
Team Focus on IROPS R2 Support
Team is Back Focus on R3
AKKA Implementation Issues
SASI new Libraries (Suddenly)
Admin Console VIPS Integration Issues
VIPS Issues
new Jenkins Affecting Deployments
AKKA Architecture Change / Reimplementation
Change SWA Source Code Repositories
November Release
QMO/DevOps Resources Transition
SWA TL Changed
Automatic Switch PDC/SDC
Admin Console - Remove Metrics / HealthCheck
QMO Perf/Soak Test Sucessful
QMO Perf/Soak Test Sucessful
QMO / UAT Functional Testing Successful