4.2 Sprint Ends
4.16 Sprint Ends
4.30 Sprint Ends
11.1 New team members expected to start 6 Dev and 1 QA
10.19 Planning Meeting to discuss fulfillment integration
11.14 Begin Integration with Fulfillment
1.31 Knowledge Data Normalized and Cleaned
1.31 Phase 1 Coding Completed
2.1 Begin UAT Training, Testing, and Defect Fixing
3.31 Complete UAT Training, Testing, and Defect Fixing
4.5 Code Freeze
4.20 Production Release
4.29 Start Migration
10.16 Sprint End
10.30 Sprint End Goal: Defect Fixes
11.13 Sprint End Goal: Regression Testing
11.27 Sprint End
12.11 Sprint End
12.25 Sprint End
1.8 Sprint Ends
1.22 Sprint Ends
2.5 Sprint Ends
2.19 Sprint Ends
3.5 Sprint Ends
3.19 Sprint Ends