13h 8min, oct 15, 2012 y - Work resumes after 35 stop work days, due to redesign of foundations and parking deck. Work is stopped for an additional 14 days over legal issues. Work begins moving smoothly ,contactor declines additional days.
Added to timeline:
River Run Timeline
By
Brantley Niven
16 Nov 2017
0
0
231
Date:
13h 8min, oct 15, 2012 y
Now
~ 11 years ago
About & Feedback
Terms
Privacy
Library
2024
©
Time.Graphics
Support 24/7
Cabinet
Get premium
Donate
The service accepts bank transfer (ACH, Wire) or cards (Visa, MasterCard, etc). Processed by Stripe.
Secured with SSL
Excellent (Trustpilot Reviews)
Based on 115+ reviews
Write your own review on
Trustpilot.com