Kipscombe Carthouse
Создана
Edward Brooker
⟶ Обновлено 6 мар 2020 ⟶
List of edits
Комментарии
События
Client Approaches my Consultancy
Feasbility and Project Brief Meeting
Concept Design Complete
Ecology Report Returned Planning & LBC submitted
Project Team appointed & Ecology Emergence Survey commissioned
Planning & LBC Verified
Site Meeting with Planning Officer and Conservation Officer
Expression of Interest specification package sent to contactors
Expression of Interest Cost Estimate Returned
Cost Estimates and Report sent to client
National Trust agree extension to planning & Planning Officer queries wedding advertisement on site
Reminder letter sent to planners for revised determination date
Ammendments requested by Conservation Officer
Formal Tenders sent to contractors
Planning and Listed Building Consent Obtained
Tenders Returned and Tender Report sent to client
Client submits initial Cost Estimates to complete initial stage of funding bid
Client submits formal funding bid
Ecologist Instructed to Complete European Protected Species Mitigation (EPSM) license
EPSM license submitted
Client Indicates funding bid likely to be approved
Natural England issue apology letter with revised determination date of 2nd December 19
EPSM Natural England License recieved
Client Informs me that funding bid has been rejected and will be resubmitted in April 2020
Building Control Site Meeting to Discuss Project
Client requests site meeting with Operations Manager
Operations Manager requests changes to proposal, I advise on implications