33
/ru/
AIzaSyAYiBZKx7MnpbEhh9jyipgxe19OcubqV5w
August 1, 2025
Public Timelines
Menu
Public Timelines
FAQ
Public Timelines
FAQ
For education
For educational institutions
For teachers
For students
Cabinet
For educational institutions
For teachers
For students
Open cabinet
Создать
Close
Create a timeline
Public timelines
Library
FAQ
Редактировать
Скачать
Export
Создать копию
Premium
Встроить в сайт
Share
Options Time Line
Category:
Иное
Обновлено:
26 фев 2020
0
0
269
Авторы
Created by
Emil Ehlert
Attachments
Comments
Network Rail
By
Emil Ehlert
26 фев 2020
0
0
252
События
Mace Appointment for Soft Strip Only
Client appoints R&D & Facade Surveys
Client appoints Structural Survey
Mace Appointment following 100% Cost Certainty
Периоды
Steel Design Period for 1st Steels
Construction Period From 1st Steel Onsite - 58 Weeks
Critical Path - Atrium Works
Critical Path Roof Works and Lift Over Run
Critical Path - Phase 2 Lifts
Critical Path - Final Commissioning
Client R&D Survey & Report
Client Facade Survey and Report
Client Structural Survey and Report
Survey Report Review and Cost Analysis
Mace Mobilisation
Scaffold in atrium
Remove the roof
Install lifting framework and roof over atrium
Roof Stripout
Strip out Basement to Lv 8
Overall Strip out period - 19 WKS
Mace Mobilisation
About & Feedback
Соглашение
Приватность
Библиотека
FAQ
Support 24/7
Cabinet
Get premium
Donate
The service accepts bank transfer (ACH, Wire) or cards (Visa, MasterCard, etc). Processed by Stripe.
Secured with SSL
Comments