16 ч 6 мин, 30 март 2020 г. - Dc5.2. PAT for RS, WDCS and PWN
3rd Station, 4th Station and 5th Station
Описание:
Complete and pass Partial Acceptance Test (PAT) for RS, WDCS and PWN, inclusive of submission of PAT test records for the facilities listed below:-
3rd Station, 4th Station and 5th Station
Добавлено на ленту времени:
Дата:
16 ч 6 мин, 30 март 2020 г.
Сейчас
~ 5 гг и 6 мес назад