7 март 2024 г. - John, We are notifying SAWS that we would like to schedule the first two sets of digesters to begin draining on 2/26/2024. We would like to get APG on the books for the first week of March 2024 to begin mobilizing. Do you recommend having a on site meeting or Teams meeting to discuss logistics of APGs scope? If you have any questions, please feel free to contact me. Best, Hugo Guillen Project Engineer Mobile 210-717-6424 Texas Office 210-694-0565 www.mgccontractors.com