Fall FYDP timeline
è stata creata
Wong jimmy
⟶ è stato aggiornato 29 nov 2017 ⟶
List of edits
Linee del tempo dal
Wong jimmy
:
30 nov 2017
0
0
395
Timeline of FYSP
Commenti
Eventi
Milestone 4: A concept design should be selected for further development (24/11)
Company Visit (1/11)
Milestone 1: Literature review and enough researches should be completed. (25/10)
Milestone 2: Target specification should be completed. (8/11)
Milestone 3: First round of concept design drawings should be completed (17/11)
Periodi
Reviews and Research (Literature review, researches on current designs in market, researches on related knowledge) (8 weeks)
Identifying Customer's Needs (4 weeks)
Establishing Target Specifications (4 weeks)
Generating Concept Designs (4 weeks)
Concept Evaluation and Selection (1 week)