seattle move
Category:
Altro
è stato aggiornato:
16 nov 2017
0
0
464
Autori
Created by
mj
Attachments
Comments
Eventi
Kick off planning meetings held 11/6-10/2017
Citrix/VDI Infrastructure Tested and Complete Inc UAT 12/26/17
Tacoma Office Facility HVAC 1/5/18
Seattle Cleanup & Exit 4/20/18
Commence wave 1/4 Associate Moves 2/15/18
Citrix/VDI Business Testing Complete 12/26/17
Network Design Complete 1/8/18
All Phases Move Complete 4/1/18
Tacoma Office Facility Carpet / Paint 1/12/18
Tacoma Office Facility Lighting / Electrical 1/19/18
Tacoma Office Facility Cubicle Config 1/26/18
Install Network/Telephony 1/30/18
Infrastructure Orders Placed 12/12/17
Identify VDI Desktop Requrements
Periodi
Install Desktops, Printers, Phones 2/12 - 3/16/18
Workstations Imaged & Shipped 1/15-1/29/18
Associate Moves 2/15/18 - 3/23/18
Disposal & Surplus of Assets 3/19-4/10/18
End User Orientation
About & Feedback
Accordo
Privatezza
Biblioteca
FAQ
Support 24/7
Cabinet
Get premium
Donate
The service accepts bank transfer (ACH, Wire) or cards (Visa, MasterCard, etc). Processed by Stripe.
Secured with SSL
Comments