10 feb 2026 anni - Hi John,
Following up on our phone conversation yesterday,
I’d like to confirm that the start date for APG’s draining operations will need to be postponed. The new scheduled start date is July 7th.
This delay is due to unforeseen issues with existing equipment at the Steven M. Clouse facility, which fall outside the scope of our work.
These equipment failures have impacted the completion of critical testing required to turn over DIG 5 and 7.
As a result, we are unable to take DIG 6 and 8 offline and be