33
/es/
AIzaSyAYiBZKx7MnpbEhh9jyipgxe19OcubqV5w
October 1, 2025
Create a timeline
Public Timelines
For education
For educational institutions
For teachers
For students
Cabinet
For educational institutions
For teachers
For students
Open cabinet
FAQ
Obtener premium
Close
Create a timeline
Public timelines
Library
FAQ
About & Feedback
Acuerdo
Privacidad
Biblioteca
FAQ
Support 24/7
Cabinet
Get premium
Donate
The service accepts bank transfer (ACH, Wire) or cards (Visa, MasterCard, etc). Processed by Stripe.
Secured with SSL
Descargar
Export
Crear una copia
Premium
Insertar en el Sitio Web
Share
TL QAD
Category:
Otro
Actualizado:
1 feb 2021
0
0
280
Autores
Created by
bodithat
Attachments
Comments
OJT Plan Rev.1
By
bodithat
23 feb 2021
0
0
213
Eventos
All Early QADS HW at Metlink
MEA network ready
Surveying stop due to covid restrictions
Surveying resume by MEA technician
ICCP Test with EGAT was postponed. EGAT ICCP was not ready.
Tentative Final report Submission, Feb 19, 2021
Request to issue letters for grant permission to work in Thailand and issue NON-B VISA for OSI team
Letters received from MEA regarding Work permit and VISA
Work permit granted from Ministry of Labour
Tentative arrival of OSI team Need 14days of quarantine
Tentative start working date of OSI team in Thailand March 5,2021
Períodos
SW Intstallation
Installation at CLD and DDE
Network Setup
Data Engineering Workshop FRTU testing (2 types)
HW setup at Metlink Office
Sub stations surveying
14 types of SRTU testing with QADS (Finished Jan 29,2021)
Tentative ICCP testing with EGAT system
Tentative FRTU testing with QADS (The rest 5 types)
Final report preparation
About & Feedback
Acuerdo
Privacidad
Biblioteca
FAQ
Support 24/7
Cabinet
Get premium
Donate
The service accepts bank transfer (ACH, Wire) or cards (Visa, MasterCard, etc). Processed by Stripe.
Secured with SSL
Comments