River Run Timeline
Creado
Brantley Niven
⟶ Actualizado 16 nov 2017 ⟶
List of edits
Comentarios
Eventos
Design Development of River Run Casino Begins
Programming development continues after internal conflicts within the Chickasaw Band are resovled.
Conceptual Design of River Run Casino Begins
Chickasaw Gaming Authority begins seeking potential contractors.
Cherokee Contractors were selected as General Contractor for River Run Casino.
Construction Schedule drafted by Cherokee Contractors.
For construction work Packages No.1- No. 12 were released
Work resumes after 35 stop work days, due to redesign of foundations and parking deck. Work is stopped for an additional 14 days over legal issues. Work begins moving smoothly ,contactor declines additional days.
Contractor and owner mutally agree on the GMP, contract is 100% legally binding now.
Back of house substantial completion
Casino Floor finishes 20 days ahead of schedule
Bill Langley proposes to accelerate opening by 17 days
Parking Garage substantial completion
New substantial completion for Casino Floor.
Original substantial completion for game room floor.
Substantial completion for Hotel.