Arbitration (SoC)
Creado
Ben TEN
⟶ Actualizado 29 oct 2018 ⟶
List of edits
Timeline desde
Ben TEN
:
5 oct 2018
0
0
367
[PI] Sanctioned Offer
29 oct 2018
0
0
301
Arb. Proc
Comentarios
Eventos
Mar 8, 2012 Agreement drawn up by R2 Made between C & R1
Jun 6, 2014 C duly completed work - accepted by R2
Jul 21, 2014 R2 issued "Practical Completion Cert." confirming completion
Jun 22, 2016 C -> R1 - issued invoice for "Retention $"
Jul 11, 2016 Au & Ass. -> R1 - "Demand Letter" for "Retention $"
Jul 26, 2016 C received - "Sch. of Defects" from R2 - "Remedial Works" - to be done w/in 21 days
Dec 14, 2016 C completed - "Remedial Works" - as a sign of good faith
Dec 18, 2016 C reported -> R2 - completion of "Remedial Works" C requests R2, upon inspection, to issue - "Cert. of Completion of Defective Works - "Final Instalment Payment Cert." C demanded - "Retention $"
Jan 25, 2017 Au & Ass. -> R1 - "Demand Letter" for "Retention $"
SoC by C: Not yet received - "Cert. of Completion of Defective Works - "Final Instalment Payment Cert."
Períodos
Jun 7 2014 - Jun 6 2016 "Defect Liability Period" - no request from R1 or R2