39 Western Larch Place 8-28-18
Создана
Josh
⟶ Обновлено 28 авг 2018 ⟶
List of edits
Комментарии
События
Doug start 10% - Total 10%
Electric meter installed
Address assigned
Purchase plans
Submit plans to HOA
Backfill house and prep for slabs
Order lumber - Floor & wall package
Order trusses
Order windows
Lumber delivered
Order flooring
Order siding
Roofing
Order Cabinets
Order drywall
Order Doors
Doug trusses set 10% - Total 30%
Doug walls up 10% - Total 20%
Doug roof complete 10% - Total 40%
Doug siding complete 10% - Total 50%
Doug sheetrock 10% - Total 60%
Doug interior trim 10% - Total 70%
Doug work complete 30% - Total 100%
Order propane tank
List on MLS
Schedule carpet
Truss delivery?
Order appliances
Периоды
Break ground - Excavate foundation and build road
Doug gone to Denver
Veele - Pour garage
Veele - Pour footings & walls
Plumbing
Electric
Heating
Patios & driveway apron
Build walls
Set trusses
Roof
Siding
Sheet, tape, texture. paint
Doors
Carpet install
cabinets install
Electric finish
Plumbing finish
Flooring install (Doug)
Tile shower
Window install
Insulation
Fireplace
Gutters
Landscaping ?
Doug build floor
Backfill house and prep for slabs
fascia & Soffit
Trim
countertop
Septic & Water Pump & Utilities
Sheet Roof