Work begins on addittional Preperation for Spray Seal works (24 ago 2020 ano – 22 set 2020 ano)

Descrição:

FH picks up additional day shifts to prepare areas for spray seal accelerated due to Covid restrictions.
1,030t of Regulation & 1,054t of 20SI across 12 sites

Adicionado na linha do tempo:

24 jun 2021
0
0
213

Data:

24 ago 2020 ano
22 set 2020 ano
~ 29 days