Detailed Saeed
Category:
História
Atualizado:
3 meses atrás
0
0
72
Autores
Created by
Saeed Youssef
Attachments
Comments
New timeline
By
Saeed Youssef
2 ago 2023
0
0
150
New timeline
By
Saeed Youssef
2 ago 2023
0
0
145
saeed
By
Saeed Youssef
5 meses atrás
0
0
74
Saeed Phases
By
Saeed Youssef
3 meses atrás
0
0
55
saeed 2
By
Saeed Youssef
5 meses atrás
0
0
41
time line1
By
Saeed Youssef
6 meses atrás
0
0
38
Time line
By
Saeed Youssef
5 meses atrás
0
0
29
Eventos
Employer’s Taking Over Date 14 May 2026
Agrupar
Group of events
Eventos
Power Transformers LOA signature date 11 Nov 2024
Powe Transformer Phase 2 Delivery 13 March 2026
Períodos
Power transformer Phase 2 Delivery
Phase 2 Milestones
Eventos
Power Transformer delivery for Phase 2 15 March 2026
HV Substation Mechanical Completion (MC) [Power transformers and associated equipment ] - Phase 2 25 April 2026
Remote End SS Works Completed 10 May 2026
Substation Hot commissioning 10 May 2026
Períodos
Phase 2 Execution Duration from :13 January 2025 till :18 May 2026
Erection Works
Agrupar
Erection Works - Phase 1
Eventos
Erection activities commencement 20 aug 2025
Erection activities Completed Phase 1 16 oct 2025
Períodos
Erection Activities
Project execution
Eventos
LOA for HV EPC Contract 13 January 204
Site Handover to Siemens 20 January 2025
HV EPC Contract Signature 31 January 2025
Outdoor Mechanical & Electrical installation Completed 30 October 2025
All Equipment Received at site Phase 1. 15 October 2025
HV Substation Mechanical Completion (MC) - Phase 1 7 November 2025
Remote End SS Works Completed 11 November 2025
Ready for Energization 18 November 2025
Períodos
Phase1 Execution Duration from :13 January 2025 till :18 November 2025
Civil Works Phase 1
Eventos
Outdoor/Switchyard foundation, Civil Work Completed 28 August 2025
Control Building Completed (Ready to receive equipment inside) 27 September 2025
Civil Works Commencement 27 March 2025
Civil Works complection 28 spetember 2025
Períodos
Civil Works on Progress
Engineering
Eventos
Enginering Commencement 16 February 2025
All Documentation Issue For Construction (IFC) 28 April 2025
Períodos
HV EPC Engineering Works
Power transformer
Eventos
Phase 1 Power Transformers Site delivery 25 September 2025
Power Transformers LOA signature date 11 Nov 2024
Períodos
Power transformer Phase 1 Delivery
About & Feedback
Acordo
Privacidade
Biblioteca
FAQ
Support 24/7
Cabinet
Get premium
Donate
The service accepts bank transfer (ACH, Wire) or cards (Visa, MasterCard, etc). Processed by Stripe.
Secured with SSL
Comments