29
/pt/
pt
AIzaSyAYiBZKx7MnpbEhh9jyipgxe19OcubqV5w
April 1, 2024
Criar
Public Timelines
Biblioteca
FAQ
For education
Cabinet
For educational institutions
For teachers
For students/pupils
Baixar
Export
Criar uma cópia
Incorporar ao site
Visualizações 192
0
0
2 escape rooms
Criada
Alla Alikina
⟶ Atualizado 24 out 2019 ⟶
List of edits
Linhas do tempo do
Alla Alikina
:
24 out 2019
0
0
172
2 cubes
24 out 2019
0
0
164
2 cubes_english
Comentários
Eventos
Funds received
Search and hiring 1. Real estate broker 2. Architect 3. Expeditor 4. Lisenced contractor
Lease signed. The deposit and the 1st month rent paid.
Equipment transfer
"Maze of Hakaina" opening
"Cursed" opening
Períodos
Equipment assemble
Lobby renovation, staff and tools rooms preparation
Filling plans and obtaining DOB permits
Phase two: Escape rooms set up. Duration: 5 months
Hiring and training
Decorations and office equipment purchase
Space search
Phase one: Preparation Duration: 2 months.
Walls framing, wiring, painting, furniture assemble
Equipment set up in "Maze of Hakaina"
Equipmnet set up in "Cursed"
Walls set up.
Equipment test in "Hakaina"
Equipment test in "Cursed"