E-Coat Permit Timeline
Criada
Juan Puerta
⟶ Atualizado 28 nov 2018 ⟶
List of edits
Comentários
Eventos
Initial Contractor Visit
New Building Permit Completed
Submit Updated Building Permit
Submit Initial Environmental Application
Initial Environmental Permit Approved
Updated Building Permit Approved
Submit Waste Management Permit
Waste Management Permit Approved
Períodos
Initial Environmental Application Preparation
Initial Environmental Application Processing by Drezdenko Authorities
Prepare Updated Building Permit
Updated Building Permit Processing
Waste Management Permit Preparation
Waste Management Permit Processing