Updated Portland Power Timeline
Editar
Atualizado 13 out 2017
0
0
396
Share
Autores
Created by
Matt Ganahl
List of Edits
Attachments
Comments
Eventos
BHE files Phase II Tariff & Rates
CPUC suspends for 30 days
Motions to Intervene Due
Prehearing conference
BHE corrected testimony due
HUS Answering Testimony Due
Rebuttal testimony due / Settlement Agreements due
HUS Corrected Testimony Due
Begin Evidentiary Hearing
End Evidentiary Hearing
Statements of positions due
210 Day suspension (Phase II End)
Earliest est. implementation of BHE TOU rate schedule
Bids due in BHE RFQ
Bid fees paid to BHE
BHE 30 day report to CPUC
HUS notified that WTE & NG/WHR bids have advanced to modelling
Begin WTE EPC development work
Raise Project Financing
BHE 120 day report to CPUC
Pyrolysis & Air Testing
Select EPC Contractor
Engineering begins
CPUC ruling on BHE ERP
Holcim execution of agreement with successful bidder in RFQ
Begin permitting process
Order Equipment
Begin Construction (WTE)
End Construction (WTE)
WTE Testing & Commissioning
About & Feedback
Acordo
Privacidade
Biblioteca
2024
©
Time.Graphics
Support 24/7
Cabinet
Get premium
Donate
The service accepts bank transfer (ACH, Wire) or cards (Visa, MasterCard, etc). Processed by Stripe.
Secured with SSL
Excellent (Trustpilot Reviews)
Based on 115+ reviews
Write your own review on
Trustpilot.com
Comments