1326 Druid Hill Time Line
Criada
Stephan Hanley
⟶ Atualizado 18 jul 2018 ⟶
List of edits
Comentários
Períodos
70% Finished plans
95% finished plans
100% finished plans
Plans updated
Need Decks plans
Submitted first deck plans (faulty)
Received Deck plans
Directly contacted Milan for structural approval
Permit issued
Permit issued - online
decided on new contractor last one couldn't fund
Picked contractor
Paid for structural drawings
Structural drawings completed
Permit approved
Revised Structural drawing height elevations wrong
new elevations for structural because height wrong
Check underpinning is succifient
Purchased/Acquired
Owner, Contractor and Arc meet at site
Kanesha started plans
Informed to start demo'd while plans never happened Marti next door scared off
Plans finalized emailed to GC no stamp
Sent check to GC for MEP (funds used for more arc drawings later)
Attempted to pull permits (failed need elevation and framing details)
Getting Kanesha to send CAD file (files continously wrong)
Sent correctly formatted CAD file myself (waiting on Murphy)
Arc sent GC PDF of plans for permit
GC confused how to print plans
Print plans myself (dads suggestion)
Informed GC not to worry about scale, submit electronically
Informed of mailing to neighbors for permits (mailed)
Uploaded and paid permit application
Again told of elevation details for deck (Murphy thought kanesha was doing it))
Uploading deck details
Floor to ceiling dimension GC informed to reach Kanesha Arc
Informed of funding issues GC
Recieved Site plan waiting for elevations and stair details (Murphy Arc)
Received Stair Detail (Murphy Arc)
Uploaded what Murphy sent Arc
uploaded compliance form, window dimensions and usps mailing
Elevations inconsistent permit denied
paperwork new contractor
Finalized GC transfer
Paid unpinning review
Reviewed underpinning results
Paid first draw to Walt
Notarized letter for underpinning review