Work begins on addittional Preperation for Spray Seal works (24 août 2020 – 22 sept. 2020)

Description:

FH picks up additional day shifts to prepare areas for spray seal accelerated due to Covid restrictions.
1,030t of Regulation & 1,054t of 20SI across 12 sites

Ajouté au bande de temps:

24 juin 2021
0
0
213

Date:

24 août 2020
22 sept. 2020
~ 29 days