Work begins on addittional Preperation for Spray Seal works (24 Aug 2020 Jahr – 22 Sept 2020 Jahr)

Beschreibung:

FH picks up additional day shifts to prepare areas for spray seal accelerated due to Covid restrictions.
1,030t of Regulation & 1,054t of 20SI across 12 sites

Zugefügt zum Band der Zeit:

24 Jun 2021
0
0
213

Datum:

24 Aug 2020 Jahr
22 Sept 2020 Jahr
~ 29 days