29
/de/
de
AIzaSyAYiBZKx7MnpbEhh9jyipgxe19OcubqV5w
April 1, 2024
Erstellen
Public Timelines
Bibliothek
FAQ
For education
Cabinet
For educational institutions
For teachers
For students/pupils
Herunterladen
Export
Eine Kopie erstellen
In der Webseite integrieren
Editieren
Einsichten 388
0
0
FYP Timeline
Wurde erstellt
Wing Kwok
⟶ Wurde aktualisiert 4 Feb 2018 ⟶
List of edits
Kommentare
Ereignisse
7/02 Meeting with Project Advisor (About Interim Report)
21/02 Meeting with Project Advisor (Report the Progress, show new data)
7/03 Meeting with Project Advisor (Show draft design, basic functioned app)
21/03 Meeting with Project Advisor (halfly done application)
6/04 Meeting with Project Advisor (Final tunes before publish)
18/04 Meeting with Project Advisor
2/05 Meeting with Project Advisor (Check for the draft)
9/05 Meeting with Project Advisor
6/05 Finish Final Report
12/05 Final Report Due Day
14/05 Final Presentation (AM) Final Demonstration (PM)
Perioden
Interim Report Due Day
7/02 - 21/02 Start develop WEB-APP (Basic Functions: MAP, Rating System)
21/02 - 12/04 Develop WEB-APP
14/03 - 1/04 Graphic Design
16/02 - 1/03 Draft Design
7/02 - 21/02 Collect Data (Photo, Location)
11/04 - 2/05 Testing the App, (Publish & Fine Tunes)
18/04 - 1/05 Writing Final Report (Draft)